Skip to content
Offshore. Fixed, deep water, and floating.

ORCA LIFT

Elevating and installation systems for offshore wind, with variants for fixed-foundation and floating platforms.

Operates from the smaller crane vessels widely available in the offshore oil and gas market. Approval in Principle from the American Bureau of Shipping for the 15 MW offshore concept.

Render of ORCA LIFT on an offshore turbine: structural chords beside the tower from the foundation to the nacelle, with a supply vessel alongside.
Project, modeled

15 MW × 67 units.

Installation campaign for a fixed-foundation project: conventional WTIV vs ORCA LIFT™.
Modeled from real project values. USD primary; EUR in parentheses.

Conventional install

2,500-ton-class WTIV, full project

$205M (€190M)

ORCA LIFT

Smaller crane vessel, scaled platform

$53M (€49M)

Saved

$152M 74%

§ 01

The vessel problem

Only five vessels in the world are suited to both installing and exchanging major components on a 15 MW turbine. They are committed to new-build work, take up to three months to mobilize, and cost about $250,000 to $370,000 a day (£190,000 to £275,000). Floating wind compounds the problem with 6,000-ton port cranes and $100M-plus port investments. Conventional weather windows limit useful working days to 40% to 60% of the calendar.

§ 02

The ORCA LIFT approach

ORCA LIFT operates from a sub-1,000-ton crane vessel with a sub-100-meter boom. The vessels are amortized, widely available in the offshore oil and gas market, and crewable locally.


The principle

The tower is largely bypassed as a load path.

Vertical lift loads travel from the platform through ORCA LIFT's structural chords into the foundation, monopile, or floater. The existing tower only sees a small stabilizing load at the flange, its strongest point, used to maintain verticality and prevent buckling on the slender chord members.

This is why a single platform serves fixed and floating foundations, most OEM platforms, and both new installation and in-service component replacement, without modification of the turbine tower design. Load modeling by Arup for fixed offshore and Kent Engineering for floating.


Operational envelope

Stable load. Wider weather window.

Once a component is fastened to the elevating platform, it is carried on a guided path, not suspended from a hook, so it does not swing. The only crane lift is the short transfer to the platform at the base of the tower, and because that lift is short, pendulum and dynamic amplification are reduced.

Conventional offshore lifts lose useful working days to weather: a 2,500-ton-class WTIV stops lifting well before the wind would otherwise stop the project. ORCA LIFT extends the operational window into wind conditions that would shut a crane lift down, converting calendar days into project days.


Foundation tie-in

Four foundation types. One platform.

01

Flush monopiles

Chords tie directly to the monopile head via a bolted transition adapter.

02

Oversized monopiles

An intermediate collar distributes load around the larger diameter.

03

Jackets

Chords land on prepared nodes at the jacket top.

04

Floating

Chords attach to a dedicated landing plate on the floater deck, outside the tower load path. Modeled by Kent Engineering on a three-column semi-submersible.

Render of the ORCA LIFT platform at the nacelle of an offshore turbine, carrying a component for exchange in place.
AT THE NACELLE · The platform carries the component to hub height and the exchange happens in place, from a smaller vessel.
Deep water

Deep water leaves no conventional option.

As offshore wind moves into deeper water, every heavy lift over a turbine's life runs into the same wall. Installing it, replacing a major component, and removing it at end of life all rely on vessels that stand on the seabed. Jack-up reach runs out at roughly 50 to 60 meters of water depth, and a fixed foundation cannot be towed to port. Past that depth, there is no established way to lift.

ORCA LIFT does not stand on the seabed. It mounts to the turbine's own foundation and carries the lift through the structural chords, so its working range does not depend on water depth. The same platform installs a turbine in deep water, services it, and decommissions it, in place, from the crane vessels already available in the market.

For developers moving into deep water, this is not an efficiency question. With no jack-up that can reach and no way to tow a fixed structure, an on-foundation platform is the only practical way to install, service, and eventually remove the turbine, and it is what CLS Wind is built for.


What it does

Built for fixed and floating fields.

01 New turbine installation, fixed and floating
02 Major component replacement at sea, no tow-to-port
03 Multi-unit parallel quayside installs
04 Avoidance of 90-plus-day turbine shutdowns from port queueing
Why it's different

Smaller vessels. Proven supply chain. Validated.

  • Smaller, available vessels

    Works from smaller, widely available vessels rather than the scarce, expensive 15 MW-class vessels.

  • Foundation-agnostic

    Lands on flush or oversized monopiles, jackets, and floating platforms, outside the existing tower load path.

  • No mega-port build-out

    Serves floating fields without 6,000-ton port cranes or $100M-plus port investment.

  • Proven supply chain

    Redeploys the offshore oil and gas vessel fleet and local crews, built on more than 70 years of jack-up engineering.

  • Third-party validated

    Load modeling by Arup (fixed base) and Kent Engineering (floating). ABS Approval in Principle for the 15 MW offshore concept.

Discuss a project

Tell us about your turbines, your sites, your timeline.